Toyo Engineering Corporation (Toyo-Japan, President and CEO Haruo Nagamatsu) has been awarded a contract for a project to construct a 54,500kW biomass power plant. This plant will be built in Yonago-shi, Tottori Prefecture, Japan for Yonago Biomass Power Generation LLC.
This plant has been developed by New Energy Development Co., Ltd. during these 2 years to construct a dedicated biomass-fired power plant using wood pellets as primary fuel. This power generation facility is a highly efficient biomass-fired plant based on the reheat system (*). TOYO will carry out the EPC turnkey contract on a full turn-key basis that includes engineering, procurement, construction and commissioning services for a power generation unit.
TOYO has positioned the infrastructure field centered on power generation plants as one of its core businesses, actively working on renewable energy power generation plants such as photovoltaic power plants and biomass power plants. This award also marks TOYO’s 3rd orders for 50,000-kW-class biomass power plants. TOYO will continue to contribute to helping create a low carbon society by expanding our approach to biomass power generation.
(*) Reheat system: Steam, after expansion through high pressure steam turbine, is sent back and reheated in the boiler, then resent to the low pressure steam turbine for further expansion. This system realizes high power generation efficiency.
Contract Summary
Client | Yonago Biomass Power Generation LLC (a LLC invested by Chubu Electric Power Co., Inc., Tokyu Land Corporation, Mitsubishi UFJ Lease & Finance Company Ltd. and New Energy Development Co., Ltd.) |
---|---|
Contractor | Toyo Engineering Corporation |
Site | Yonago-shi, Tottori, Japan |
Facilities | 54,500kW dedicated biomass-fired power generation facility |
Scope | Turnkey contract for engineering, procurement, construction and commissioning services |
Completion | Scheduled for 2022 |