We, Toyo India, are pleased to announce the successful completion of the 5 MMTPA LNG Regasification Project (10 to 15 MMTPA capacity expansion) for Petronet LNG Limited (PLL) at Dahej in Gujarat. This Project extends Toyo-India’s long-standing relationship with PLL, being associated right since their Phase-1 (5 MMTPA capacity) LNG Regasification Terminal at Dahej.
The journey of this prestigious Project started on 31st January 2014 and we have successfully achieved start-up of production on 4th August 2016, which is 3 months and 28 days ahead of the scheduled start of production date.
While in the process of overcoming the challenges throughout the Project, we also achieved 7.7 Million safe man-hours without Lost Time Injury (LTI) until completion of this Project.
The key factors practiced for successful Project completion:
• One Team
• Solutions First
• Ownership
• Positive Approach.
With the completion of this project Toyo-India has established itself as a forerunner EPC contractor in the LNG business in India.